30 Oct 1999

Fortum Engineering – Suceava project

Client: Fortum Engineering, Finland
Project Country: Romania
Project: Rehabilitation of Suceava Power Plant, 2×50 MW

Engineering
For the rehabilitation project of Iaşi Power Plant, we have provided some detail design services for the mechanical systems.

Procurement
From a procurement perspective we have provided components for mechanical and electrical systems but also for the civil works. We have fabricated components for the mechanical system.

Construction
We have performed the erection of furnace walls (on the old burner openings), furnace walls for the new coal burners, coal mills, coal dust piping system, the new burners, primary and secondary air ducts systems, but also the recirculated gas ducts, fans, actuators. This was together with the primary cold air system, insulation work and stairs & platforms. From the electrical procurement material TSB performed election of the complete electrical, automation and instrumentation systems. To tie this up, TSB was also responsible for the erection of civil works